1. Go to the seminar collection.
  2. Open the Spreadsheet 01 - Your first Script. Make a copy and save it.
  3. In your Spreadsheet, click on the 'Tools' menu, then select 'Scripts' and 'Script editor...'.

    The Script editor wil pop up as a new window. Move the windows so that you can simulaneously visualize both the Script Editor and the Spreadsheet.


  4. Run the script example and see what happens! Select the function example from the Combo box at the top of the Editor then click on the 'Run' menu, then 'Run selected script'.

  5. A dialog box should pop up in the Spreadsheet and request you to enter a number. Enter one and click 'Ok'.
  6. Then, the spreadsheet cells A1 and B1 are updated. Finally, a second dialog box shows the value you entered plus 1.